Special Town Meeting will vote Oct. 19 on appropriating the $325 million in funds needed to go forward with the Pollard Middle School project. Here’s a look at the process and the key considerations.
What is Town Meeting voting on?
The Massachusetts School Building Authority requires municipalities to obtain spending authority for the entire cost of a project. So, even though the town is in line to receive $80.6 million in state reimbursements from the MSBA, Special Town Meeting’s Article 1 is asking members to “vote to raise and/or transfer and appropriate the sum of $322,655,945 to construct a new Grade 6-8 Pollard Middle School.”
How many votes are needed to approve?
The vote at Town Meeting on Oct. 19 requires a two-thirds majority of members who are present and vote.
Why is there also a Pollard ballot item for Needham voters in the November election?
The townwide vote on Nov. 3 is a “debt exclusion override” to authorize the town to override the limitations of Prop. 2½ to borrow the money. The ballot language does not specify any dollar amount, but the project is expected to require borrowing $244.8 million that will be paid back over 35 years. The debt exclusion override needs only a simple majority to pass.
The MSBA provides a 120-day window for a project to have its funding approved by Town Meeting and the voters. That window closes Dec. 24.
What happens if either the Town Meeting article or the override election ballot question do not pass?
If either the Town Meeting article or override election ballot question fail, the town is given 10 days to communicate reasons for a failed vote to the MSBA, along with possible remedies.
The MSBA could allow a revote on the same project — not a revised or scaled-back project, as changes cannot be made to the educational program or project size before a new vote. Failing a successful revote, the town would withdraw from the MSBA program and submit a new Statement of Interest, which could mean a multi-year delay.
The Nov. 3 election will occur regardless of the outcome at Town Meeting. If the Town Meeting vote fails but the ballot question passes, the town has the option of convening another special Town Meeting for a second vote.
Town Manager Katie King was asked at the Oct. 7 Finance Committee meeting what would happen if Town Meeting approves the spending but the electorate does not vote to approve the override. “Then the project does not move forward,” she said.
Why is the project so expensive?
Public construction is generally more expensive than private building. Public projects operate under a different set of labor rules, procurement laws, design requirements, oversight procedures and risk allocations. While the work is performed by private companies, they do not have as much autonomy in areas such as selecting sub-contractors and utilizing established supply chains.
Costs are also rising rapidly. According to the U.S. Bureau of Labor Statistics, the national price index for new build construction has risen by 60% in the past 10 years.
More specific to Pollard, this will be a big school. Needham’s middle schoolers account for roughly 25% of total enrollment, necessitating a facility that can house just over 1,300 students.
Certain project components, like a geothermal heating-cooling system and a 750-seat auditorium are costly elements of the Pollard project for which the MSBA will provide little to no reimbursement.
The geothermal system will pay for itself over time. A heating-cooling system is an essential component of any new building plan, and the geothermal system was chosen for its long-term value after the town conducted a life-cycle cost analysis. The system also could be eligible for MassSave program incentives and IRA tax credits.
An auditorium or equivalent space was deemed important to support the schools’ performing arts curriculum. The auditorium size was based on existing educational programs and community demand for a modern theater space.
What is the town’s rationale for the project? What other options were considered?
The School Committee master plan contends that the 70-year old Pollard is outmoded and so worn out that it is neither a cost-effective nor time-effective candidate for renovation.
Looking at the big picture, school officials view a 6-8 middle school as the superior option both educationally and financially for the entire school system. School officials claim it better facilitates plans to address the even older and similarly distressed Mitchell Elementary School by leaving the High Rock building available to assist with that project.
The town studied options for base repairs, additions/renovations on Harris Avenue, new buildings with multiple construction phases/durations on Harris Avenue, and a new building at DeFazio Park. The latter option was eliminated following a vote from the Park & Recreation Commission opposing construction on the proposed site. Other options were dismissed for added long-term costs, failure to meet project goals, lengthy construction timelines and inability to preserve the sixth-grade center.
What are opponents saying?
Although the Finance Committee voted 5-4 to recommend that Town Meeting support the funding, the four dissenting members offered several reasons for declining to back the project.
Opponents believe cost should have been the primary driver of the project, asserting the schools designed a plan before establishing how to pay for it.
Some Finance Committee members echoed sentiments of residents who feel that the project is too big, too costly and will have an adverse impact on the town’s finances for a generation. They fear it will starve the operating budget and risk postponing or even foregoing other town capital investments that require incurring debt.
There is considerable concern that the financial burden on “house rich/cash poor” residents, especially seniors, may force them to sell their homes due to rising property tax bills.
While the schools’ planning process led to support for a 6–8 school, some of those opposed suggest the Grade 7–8 model should have been more seriously considered. They oppose mothballing High Rock because the 6th grade-only option has proven popular with many parents and keeps the High Rock school occupied.
What are the implications for the High Rock School and Mitchell Elementary School?
The school’s master plan rests on Pollard reverting to a 6–8 school. Freeing up High Rock is intended to provide flexibility when the town turns its attention to planning for the future of Mitchell — almost a decade older than Pollard and also near the end of its useful life.
Having High Rock available to serve as a temporary school would greatly lessen the costs of any future Mitchell project. If it turns out that renovating or rebuilding Mitchell is cost-prohibitive or otherwise not recommended, High Rock could replace it.
It could serve as a sixth elementary school should town demographics trend in a direction that would suggest that configuration, or it could also be utilized if the state were to pass a law mandating universal voluntary preschool.
Is there any relief for taxpayers if the accompanying increase proves unaffordable?
Yes, for eligible homeowners. Elderly and Disabled Taxation and Property Tax Assistance Funds exist to offset tax burdens for low-income, low-asset homeowners, aged 60 + or with a disability. Tax exemptions are available for particular homeowners, such as elderly or blind individuals, disabled veterans and widows or widowers. The Council on Aging also coordinates the Senior Tax Work Off program, which allows senior residents to work for the town up to 100 hours a year and have earnings credited to their property tax bill.