The construction of a new playground at the Eliot Elementary School leads the list of four projects totaling more than $2.5 million that the Community Preservation Committee voted on March 18 to submit for Town Meeting’s approval when it convenes in May.
If the Eliot project is approved and its ambitious project schedule is met, the playground could be ready for the start of the 2026-27 school year.
The CPC’s requests include funding for new roofs at the Needham Housing Authority’s Seabeds Way complex, the purchase of 10 acres of open space near Ridge Hill Reservation and a study on the feasibility of adding a disc golf course to Needham’s recreational offerings.
Community Preservation Act funds are derived from a 2% surcharge on property tax bills which generates more than $4 million annually. The funds can only be used for purposes allowed under the CPA and are restricted to spending on open space protection, recreation, historic preservation and the provision of affordable housing.
The Eliot project, a joint request from Needham Parks & Forestry and the Park & Recreation Department, seeks $1.44 million to create a safer, more accessible play space at Eliot.
The project that was recommended for funding was a scaled-down version of the original submission which included a one-phase rebuild of playground structures (built in 1956, rebuilt in 2003), adjoining basketball courts and athletic field.
New cost estimates for the Eliot playground application were reviewed by the Community Preservation Committee on March 11, with the non-playground elements deferred to a future second phase.
The active project prioritizes playground renovations, dropping the original $3.5 million ask from the CPC to the $1.44 million request for phase one.
“When we came to you folks last year for design, it was for a one-phase, much larger project — playground, field, courts,” said Stacey Mulroy, director for Park & Recreation, on March 3. “Since then, we have phased it.”
Mulroy added that the decision to phase the project was due in part to CPC’s inability to appropriate funds for synthetic turf on the athletic field. CPC funds can only be used on natural grass fields.
The $1.4 million in CPC funding will cover a new poured-in-place surface, the addition of ADA-accessible structures and additional elements for shade and seating.
“If we are so fortunate, we will break ground July 1 when the funds become available, and do the ‘summer slammer’ and get the playground operational before school opens,” Mulroy said.
During the presentation, Mulroy and Superintendent of Parks & Forestry Ed Olsen emphasized the approval of the superintendent, school committee and parent-teacher council. Karen Bourn, Eliot’s principal, spoke up from the meeting’s public Zoom to voice support for the project, noting that certain areas of the playground have become unusable over the years.
“Playgrounds have a shelf-life, and we have exceeded this one,” Mulroy added.
In discussions following the presentation, CPC members said playground drawings looked good, the increased safety of new designs was compelling, and they felt Olsen and Mulroy had a reasonable basis for cost estimates — “And these playgrounds are kind of expensive these days,” acknowledged CPC chair Dave Herer.
Seabeds Way roofs
The second-largest award was the $804,000 recommended to support the NHA’s $20 million preservation and modernization of the 46 units located in the four NHA buildings at 22-46 Seabeds Way. Built in 1982, the buildings are long overdue for extensive maintenance.
The NHA has secured funding from multiple sources, including $3.2 million in prior CPC funds, and expects to award the contract in June. The overall scope includes replacement of bathrooms and kitchens, updating electrical and heating systems and replacements of stairs, railings and ramps.
The $804,000 will fund roof replacements to support electrical upgrades to prepare for on-site solar power generation. There was concern that the current roofs would be beyond their useful life and not be able to support the anticipated 25-year life of the new solar systems, creating a risk of water infiltration and subsequent damage.
When work is completed, Seabeds will have energy-efficient, all-electric buildings with improved ventilation and air-source heat pumps for heating and cooling.
The project will be the first work done under the NHA’s long-term Preservation & Redevelopment Initiative intended to upgrade most of the NHA’s 336 units at its sites at Seabeds Way, Captain Robert Cook Drive, Linden-Chambers and High Rock Estates.
Cartwright Road
The CPC is asserting its open space acquisition authority to seek $300,000 that will be combined with $500,000 from the town’s Conservation Trust to purchase 10 acres of open land off Cartwright Road adjacent to the town-owned Ridge Hill Reservation.
The Select Board in February voted unanimously to approve the use of the Conservation Trust to support the purchase of the property and to designate it as undevelopable open space.
The CPC had expected to allocate an additional $2.5 million in this cycle from its open space reserve to purchase a 37-acre parcel adjacent to the Town Forest from a scouting organization, but that sale has not been consummated.
CPC Chair David Herer told the CPC at its March 18 meeting that the discussions around that sale are continuing and he anticipates an off-cycle request to be submitted at Special Town Meeting in the fall.
Disc golf
The fourth project was sponsored by Park & Rec and seeks $50,000 for a study of the feasibility of creating a disc golf course in town.
There is a robust disc golf community in town which funded its own feasibility study of two potential areas in Ridge Hill and the Town Forest respectively. The proponents noted that the sport is low impact, low maintenance and compatible with other uses of town open space — hiking, walking, biking, etc.