More than 60 people turned out for the Park and Recreation Commission’s open forum on the proposed location for an action park and pickleball courts, and they had a clear message: Build them at Claxton Field.
The Sept. 9 public forum featured a presentation of the Active Recreation Feasibility Study conducted for the town by CHA Consulting. The study was the result of recommendations made in 2023 by the Active Recreation Assets Working Group that found residents were most interested in having an action sports park and pickleball courts. The May 2023 Town Meeting approved $35,000 for the feasibility study as a first step in planning for such facilities.
CHA president Asa Beckman presented a PowerPoint that gave an overview of the project, which would have an area designed for skateboarding and related activities such as rollerblading, along with a pump track for different kinds of wheeled sports. It also would have a separate area for pickleball courts.
Town officials and CHA staff reviewed possible sites for the facility and considered four locations — the former Hillside School and Cricket, Claxton and Mills fields. Based on considerations such as accessibility, parking, noise levels and existing utilities, they concluded that only Claxton and Mills merited further study.
Mills Field neighbors, however, spoke out strongly against adding more activity and noise there. Julie Tracey, who lives on Beech Street adjacent to the park, said she appreciates the town’s recognition of the need for more recreational spaces, but said Mills already has too much happening. She asked when the feasibility study was conducted. “Was it done during one of the nightly baseball games when dozens of spectators line the infield and outfield? Was it during any summer evening when kids are riding bikes and playing basketball? Was it the party for the pickleball players when all of this is going on?” She said if they had visited during these times they would have seen there’s too much activity there to add more.
David Mindlin, who also lives across from the park on Hampton Street, called Mills Field a gem. “It’s a beautiful little neighborhood. I love waking up to the sound of baseball bats at 9 o’clock in the morning on weekends — not at 5 or 6 o’clock the way we hear the pickleball courts.” He said something of this scope is not appropriate for that neighborhood. “Claxton Field is a marvelous location for this project.”
Several speakers cited the constant noise from pickleball as a reason to choose Claxton, where there are no neighbors to disturb. The pickleball players attending the meeting agreed. By a show of hands, more than a dozen of them said they unanimously favor locating the facilities at Claxton.
Joining the meeting by Zoom, 11-year-old Joanie expressed enthusiasm for the skate park. “It’s kind of hard to skateboard because I need to go on the sidewalks and in parking lots; that’s not super safe. Sometimes the sidewalks are bumpy. I think it would be a good idea to have a skate park because it makes it more accessible.”
In addition to comments, several individuals asked questions about specifics of the project, and Parks and Recreation Commission chair Chris Gerstel said he would respond with answers in the next several weeks. The next step is to finalize the location and begin to conceptualize designs. “I think we heard pretty clearly that there is one area that is preferred over the other,” said Gerstel. “Claxton is probably the most preferable space for not only one user group but all of the user groups.”
Gerstel said he hopes to submit an application to the Community Preservation Committee by Nov. 1 to fund a design for the park. The design would be presented at another public forum for feedback, likely a year from now. Once the design is approved, Gerstel said the commission would seek town funding for construction. If all goes well, park construction could begin in 2026.